Tianye Chemical Company successfully completed a total of 427 inspections in autumn

At 12 o'clock on the morning of November 13th, with the normal power transmission of the ionization membrane workshop rectifiers of chemical companies, it marked that after 3 days of hard work, Tianye Chemicals 240,000 tons/year of PVC resin and 180,000 tons/year of ion-exchange membrane caustic soda The joint chemical project successfully completed the 2013 annual parking overhaul task, laying a solid foundation for the company's rapid development and sprinting its annual production targets.
Tianye Chemical Industry Co., Ltd. is a national Class A fire and explosion protection unit. It has a variety of dangerous and explosive devices and equipment. According to the production needs, it is required to conduct two shutdown inspections every year to ensure the confidential performance and safety performance of the equipment.
It is reported that this autumn equipment overhaul is the second annual shutdown maintenance, a total of 427 projects, of which 48 major maintenance projects, a technical transformation, more than 10 equipment transformation. Compared with the previous maintenance, the maintenance time is tight, the task is heavy, and the personnel are tense. To complete the maintenance task ahead of schedule and sprint to the target mission of the whole year, the company’s general manager Zhu Jiangjun comes to the front line of inspection and maintenance, on-site guidance, and the various sections are responsible. People went into the front line and the outsourcing units worked in close cooperation and worked together. Everyone gave up the rest time, raced against time, battled day and night, and completed the equipment overhaul task one day ahead of schedule.
Zhu Jiangjun, general manager of Tianye Chemical Company, pointed out that this autumn overhaul is a full-scale and meticulous maintenance carried out before the arrival of this winter. In order to increase the production capacity of the plant, the production of high-yield, stable production is completed. Tasks to achieve zero production safety accident guarantees throughout the year, the company through advanced planning, scientific arrangements, safe construction, harmonious maintenance, grasping details, strong management and other powerful ways, combined with the actual repair, adjust the maintenance schedule at any time, high standards to complete the maintenance work.
Due to the company's effective organization and measures in place, the planned maintenance task was successfully completed and a beautiful battle was fought. Through this overhaul, production, equipment, and safety hazards have been completely eliminated, which has laid a solid foundation for the successful completion of the “four-quarter sprint in the fourth quarter” labor competition. Tianye Chemical Company will inevitably create high-yield and stable production, and innovate again. Excellent performance, to make more and more contributions to the group company.